Oracle may start paying for data center that doesn’t exist yet – New Mexico’s Jupiter project delayed

Olivia Bennett by Olivia Bennett
September 25, 2026
in Technology
0
Oracle may start paying for data center that doesn’t exist yet – New Mexico’s Jupiter project delayed
0
SHARES
6
VIEWS
Share on FacebookShare on Twitter

Events surrounding Oracle this week have some investors wondering whether the “ring trade” popular in the artificial intelligence craze has begun to unravel. Due to force majeure, Oracle was unable to build a data center in New Mexico on time and is currently requesting deferral of lease and loan payments.








New Mexico data center reportedly dubbed ‘Project Jupiter’ financial timeswas supposed to be operational by the end of 2028, but now faces protests from local residents over the construction of the necessary energy infrastructure. Due to these reasons, the implementation of the project was delayed and Oracle was unable to become operational within the initially agreed time frame, so the company requested a deferment of payments to its partners and contractors – the Blue Owl Capital (Stack Infrastructure) unit involved in the construction of the core facilities and the parent investment company Blue Owl Capital. In addition, even if the facility is not built on time, Oracle will have to repay an $18 billion loan plus interest.

    Image source: Oracle

Image source: Oracle

The terms of the contract mean that Oracle has a financial obligation to the partners for rent amounts deferred for three years, inclusive, regardless of when construction is completed. The first phase of Project Jupiter is scheduled to begin work in the first half of 2027, so even the slightest delay would seriously increase Oracle’s risks. The company has notified its project partners of the occurrence of force majeure, but when commenting to the media, it prefers to comment on the situation only in the spirit of guaranteeing compliance with the original timeline: “The Jupiter project is proceeding as planned. We remain committed to the New Mexico project and are confident in our future trajectory.”.

If the power supply to the facility under construction is not established on time, Oracle will have to pay periodic payments despite the fact that the data center will not be able to operate. Project Jupiter is part of an initiative OpenAI support Computing power totals $300 billion. Formally, Oracle could transfer liability for lease payments to Blue Owl Capital’s construction arm, but it would have to repay the loan in full, and Blue Owl’s financial arm would also be able to demand periodic payments of the principal portion of the debt.

Lawyers now wonder whether it is appropriate to use force majeure to renegotiate the mutual obligations of the parties to a transaction. To finance the construction of the data center, a consortium of more than 20 banks provided an $18 billion credit line late last year. It was initially expected that this financial burden would be redistributed among more institutional investors, but due to growing concerns among the latter, the plan did not work. The debt loads on both sides of the deal are higher than they initially expected. The deal’s debt value on the interbank market was no more than 90 cents on the dollar, according to the Financial Times. The initial interest rate on the four-year loan is 2.5 percentage points above the benchmark overnight borrowing rate on Treasuries. The loan term can be extended for another two years.

Blue Owl Capital has invested $3 billion in the project and will earn annual interest income of 9% during the construction phase and approximately 11% once the facility is operational. If Oracle manages to convince the partner that a force majeure situation has occurred, it can extend the payment period after the discount. Additional payments will begin later. In any case, Oracle faces situations where costs increase as project deadlines increase and revenue starts to come in later than planned. This makes it necessary to reconsider agreements with partners on the grounds of force majeure.

Construction delays at the New Mexico data center were also due to technical difficulties, as pipes needed to be laid on site for air supply to the fuel cell power plants of the future. The data center’s projected energy consumption must exceed 2.4 gigawatts, so creating adequate energy infrastructure will also take time. Against the backdrop of such rumors, Oracle shares fell nearly 3.5% in U.S. trading.

If you find an error, select it with your mouse and press CTRL+ENTER. |Can you write better? We always welcome new authors.

Source:

Related Posts

Blizzard gives away rare resources from Diablo 4 as compensation for server outage
Technology

Blizzard gives away rare resources from Diablo 4 as compensation for server outage

by Olivia Bennett
September 26, 2026
Hell of Us: Nintendo Switch 2 launch delayed
Technology

Hell of Us: Nintendo Switch 2 launch delayed

by Olivia Bennett
September 26, 2026
It looks like the results are good: Ace Combat 8: Wings of Tef has been highly praised by gaming journalists
Technology

It looks like the results are good: Ace Combat 8: Wings of Tef has been highly praised by gaming journalists

by Olivia Bennett
September 26, 2026
Action shooter SYNDUALITY: Echo of Ada’s servers are shutting down, but you can play offline
Technology

Action shooter SYNDUALITY: Echo of Ada’s servers are shutting down, but you can play offline

by Olivia Bennett
September 26, 2026
Details on the latest game event for Battlestate Games’ shooter Escape from Tarkov
Technology

Details on the latest game event for Battlestate Games’ shooter Escape from Tarkov

by Olivia Bennett
September 26, 2026
Next Post
Intel catches up with TSMC in the nanometer race – the difference between Intel 14A and TSMC A14 is no more than 5%

Intel catches up with TSMC in the nanometer race - the difference between Intel 14A and TSMC A14 is no more than 5%

Fast aerial delivery turns out to be too noisy: Texas residents complain about Amazon drones

Fast aerial delivery turns out to be too noisy: Texas residents complain about Amazon drones

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *


Math Captcha
÷ one = three


Editor’s Choice

TSMC is ready to produce chips smaller than 1.4nm

TSMC is ready to produce chips smaller than 1.4nm

September 20, 2026
HUAWEI nova 16s and FreeBuds Neo have been pre-ordered in Russia, and MatePad Air is now on sale

HUAWEI nova 16s and FreeBuds Neo have been pre-ordered in Russia, and MatePad Air is now on sale

September 24, 2026
OpenAI calls on the U.S. to develop mandatory national artificial intelligence safety standards

OpenAI calls on the U.S. to develop mandatory national artificial intelligence safety standards

September 10, 2026

Browse by Category

  • Games
  • Technology

Browse by Tags

action Add to adventure announcement Chronicles of Antiquity CNC company cooperative detail emulator fear Game play Gamescom 2026 Global version interview in the mall Ltd. Massively multiplayer online role-playing game mobile Multiplayer Multiplayer online competitive games Netmarble new role new season nintendo switch nintendo switch 2 personal computer Playstation 5 release Release date renew role playing games sandbox shooter snowstorm steam Strategy Survive test Tokyo Game Show 2026 trailer video Xbox Series XS XL Games ZBT
Aroged

Aroged Gaming, Technology & AI News, Reviews, Guides, Trends and Digital Innovation. Stay ahead with the latest updates shaping the future of gaming and technology.

Categories

  • Games
  • Technology

Browse by Tag

action Add to adventure announcement Chronicles of Antiquity CNC company cooperative detail emulator fear Game play Gamescom 2026 Global version interview in the mall Ltd. Massively multiplayer online role-playing game mobile Multiplayer Multiplayer online competitive games Netmarble new role new season nintendo switch nintendo switch 2 personal computer Playstation 5 release Release date renew role playing games sandbox shooter snowstorm steam Strategy Survive test Tokyo Game Show 2026 trailer video Xbox Series XS XL Games ZBT

Recent Posts

  • Blizzard gives away rare resources from Diablo 4 as compensation for server outage
  • Hell of Us: Nintendo Switch 2 launch delayed
  • ‘The Last of Us: Season 3’ includes original Abby and Lev actors, but in different roles
  • About Us
  • Copyright Policy
  • Disclaimer
  • Terms and Conditions
  • Privacy Policy

© 2026 Aroged. All Rights Reserved.

Powered by
►
Necessary cookies enable essential site features like secure log-ins and consent preference adjustments. They do not store personal data.
None
►
Functional cookies support features like content sharing on social media, collecting feedback, and enabling third-party tools.
None
►
Analytical cookies track visitor interactions, providing insights on metrics like visitor count, bounce rate, and traffic sources.
None
►
Advertisement cookies deliver personalized ads based on your previous visits and analyze the effectiveness of ad campaigns.
None
►
Unclassified cookies are cookies that we are in the process of classifying, together with the providers of individual cookies.
None
Powered by
No Result
View All Result
  • Home
  • Games
  • Health
  • Technology
  • World

© 2026 Aroged. All Rights Reserved.

Go to mobile version